Statute of Limitations for Construction Defects in Idaho
1 min read
Published April 8, 2025 • Updated May 16, 2026 • By DocketMath Team
Trust release 4
This page has legal or numeric text that still needs claim-level inventory before we can treat it as verified.
How the limitation period applies
The controlling primary authority for US-ID construction defects SOL (5-241) is 5-241.
5-241. Tort actions, if not previously accrued, shall accrue and the applicable limitation statute shall begin to run six (6) years after the final completion of construction of such an improvement
Use the calculator
DocketMath's statute-of-limitations tool can model these timelines once you identify the controlling claim type and accrual date. Use the source panel for the verified primary-source citations.
Open the Statute of Limitations calculator
Sources
All sources are official primary law published by legislature.idaho.gov.
Corroboration method: government_primary_source_direct_fetch.